Friday, February 20, 2026
15.1 C
New Delhi

Pune company’s Delhi-Mumbai express-way contract may be axed over delays

Pune company's Delhi-Mumbai express-way contract may be axed over delays

Pune company’s Delhi-Mumbai express-way contract may be axed over delays

NEW DELHI: The National Highways Authority of India (NHAI) on Wednesday slapped an “intention to termination notice” – the final procedure before termination – on Roadways Solutions India Infra Ltd (RSIL) for failing to meet the construction target of a 35-km stretch of the Delhi-Mumbai Expressway. The physical and financial progress on this stretch in Gujarat was barely 4.9% and 4.6%, respectively, of the target.The progress on two other stretches – 27 km and 25 km – being constructed by the company in the state is at 23% and 36%. The dismal pace of construction may push the revised deadline of the project beyond March 2028, sources said.Pune-based RSIL is an engineering and construction company that operates mainly in the roads and highways sector. The company had bagged the packages of the expressway in Gujarat in 2021.Suprisingly, NHAI had terminated the contract of RSIL for two stretches in March 2023 and then re-awarded them to RSIL in Nov 2023 after it again put in the lowest bid. TOI on Feb 14 had first reported how the slow progress on these three stretches, with a total length of 87 km in Gujarat, was delaying the over Rs 1 lakh crore project.In a letter to RSIL, NHAI said the “intention to termination notice” has been issued on account of contractor’s “absolute and continued non-performance”. It said, “…despite the contractor having been granted repeated indulgences and more than adequate opportunities through the execution of three settlement agreements, the contractor has achieved a negligible financial progress of only 4.59% (after lapse of 16 months from the appointed date of Aug 31, 2024)”.The letter said that as per the originally envisaged timeline of 18 months commencing from Aug 31, 2024, the contractor ought to have achieved approximately 70% financial progress. Mentioning how little progress has been made even after 16 months conclusively establishes that completion of the Jujuwa-Gandeva section of the expressway by Nov 15, 2026 “is wholly impossible”, it said.The highways authority claimed that despite granting repeated opportunities and its extended assistance to the contractor, it “failed to demonstrate any improvement or to achieve the requisite progress”. It said that even after three settlement agreements, the contractor failed to meet targets. “In the settlement agreements, it was specified that if it fails to achieve agreed milestones, NHAI will terminate the contract without any cure period notice. So, we have served the notice,” said an official.Cure period notice is issued to a contractor to fix any breach in 60 days. NHAI said the communication may be treated as a “15-day notice”, as per the contract agreement, and after the expiry of this period, the authority “shall be entitled to terminate the contract agreement”. It has also said the incomplete three packages under RSIL are creating significant public inconvenience across multiple fronts. In the case of two other sections, NHAI is likely to give a cure period notice to RSIL.

Go to Source

Hot this week

‘One must know how to receive forgiveness’: Venezuelan parliament passes amnesty law

The law is meant to apply retroactively to 1999 — including the coup against previous leader Hugo Chavez, the 2002 oil strike, and the 2024 riots against Maduro’s disputed reelection — giving hope to families that loved ones will fi Read More

Trump says he ‘doesn’t know if aliens are real’ but orders release of data on UFOs

It is, however, not clear whether the files will be released to the public yet. Read More

Quentin Griffiths, Founder Of Fashion Giant Asos, Dies In ‘Mysterious Fall’ In Thailand: Reports

Asos co-founder Quentin Griffiths died after a fall in Pattaya, Thailand. Police found no disturbance but haven’t ruled out foul play. Read More

Who Is Namgya C Khampa? Diplomat Who Represented India At First Meeting Of Trump’s Board Of Peace

According to Ministry of External Affairs (MEA), Namgya C Khampa is an Indian Foreign Service (IFS) Officer of the 2000 batch. Read More

Topics

‘One must know how to receive forgiveness’: Venezuelan parliament passes amnesty law

The law is meant to apply retroactively to 1999 — including the coup against previous leader Hugo Chavez, the 2002 oil strike, and the 2024 riots against Maduro’s disputed reelection — giving hope to families that loved ones will fi Read More

Trump says he ‘doesn’t know if aliens are real’ but orders release of data on UFOs

It is, however, not clear whether the files will be released to the public yet. Read More

Quentin Griffiths, Founder Of Fashion Giant Asos, Dies In ‘Mysterious Fall’ In Thailand: Reports

Asos co-founder Quentin Griffiths died after a fall in Pattaya, Thailand. Police found no disturbance but haven’t ruled out foul play. Read More

Who Is Namgya C Khampa? Diplomat Who Represented India At First Meeting Of Trump’s Board Of Peace

According to Ministry of External Affairs (MEA), Namgya C Khampa is an Indian Foreign Service (IFS) Officer of the 2000 batch. Read More

Ramadan 2026: City-Wise Iftar And Sehri Timings In India Today

Muslims will fast each day from Sehri (around 5:39 AM in Delhi) until Iftar (around 6:13 PM), with timings differing by city. The holy month will conclude with Eid on March 20. Read More

Ramadan 2026: Mezze To Desserts, Popular Iftar Dishes From Around the World

Ramadan 2026 Recipes: From mezze and biryani to baklava and kunafa, explore popular iftar dishes enjoyed around the world. Read More

Stone-Pelting In Jabalpur: Clash Erupts Near Temple and Mosque In Sihora, Police Deployed

Communal tension erupted in Madhya Pradesh’s Jabalpur district after a youth allegedly vandalised the grill of a Durga temple, sparking a dispute between two groups that turned violent late Thursday night in the Sihora are Read More

Related Articles