Mumbai-Ahmedabad Bullet Train: First Phase Set To Start In December 2027

Curated By :

Last Updated:

Railway Minister Ashwini Vaishnaw said that the first section of the high-speed corridor on the Surat-Bilimora section will start in December 2027.

Railway Minister Ashwini Vaishnaw Called it a

Railway Minister Ashwini Vaishnaw Called it a “landmark achievement”

A major breakthrough has been achieved in the Mumbai–Ahmedabad Bullet Train project with the completion of around 5 km ( 4.88 km) tunnel between Ghansoli and Shilphata. Railway Minister Ashwini Vaishnaw, who was also present on the site on Saturday morning, called it a “landmark achievement”.

He also said that the first section of the high-speed corridor on the Surat-Bilimora section will start in December 2027.

Recommended Stories

Vaishnaw hailed the project while speaking to the reporters and said that the bullet train will be the “transport for the middle class”, and the fares will be “reasonable”.

“Today, an important milestone has been achieved in the Mumbai-Ahmedabad bullet train project. An undersea tunnel is being constructed beneath the creek between Mumbai and Thane… A crucial 4.8-kilometre section has achieved a breakthrough today… This is a very important milestone for the entire project,” Railway minister told reporters.

He said that the Google Maps app shows the journey time between Mumbai and Ahmedabad as nine hours, but people will be able to cover the distance in two hours and seven minutes on the bullet train.

The first phase of the bullet train project will be first launched on the Surat-Bilimora section in 2027, covering Thane in 2028 and the Bandra Kurla Complex in 2029, Vaishnaw said.

“The services are designed such that a train will depart every half hour during the morning and evening peak hours. Once the entire network stabilises, there will be a train every 10 minutes during peak hours,” he said.

There will be no need for ticket reservations for travel between Mumbai and Ahmedabad, and passengers can arrive at the station and board, the minister said.

Standing at one of the openings of the tunnel, Vaishnaw pushed the button and triggered a controlled dynamite blast to break through its final layer, completing five km of excavation.

The National High Speed Rail Corporation Limited (NHSRCL) said that the tunnel, excavated using the New Austrian Tunnel Method (NATM), is part of the 21 km underground stretch between the Bandra-Kurla Complex (BKC) and Shilphata, including a 7-km segment beneath Thane Creek.

With the latest breakthrough, the bullet train tunnel now connects the Savali shaft to the tunnel portal at Shilphata, linking it to the viaduct portion of the Mumbai-Ahmedabad High Speed Rail (MAHSR) project, the NHSRCL stated in a release.

The NHSRCL said that excavation of the tunnel began in May 2024 in three phases, and the first breakthrough of a 2.7 km continuous section was achieved on July 9. An additional intermediate tunnel (ADIT) was built to allow simultaneous excavation from both Ghansoli and Shilphata sides.

The NATM tunnel has an internal width of 12.6 metres and was constructed using drilling, blasting, survey works, and support systems under challenging geological conditions, it stated.

The corporation said that the next phase will involve waterproofing, lining, finishing, and equipment installation, while the remaining 16 km of tunnelling will be executed using tunnel boring machines (TBMs).

The completed tunnel will be a single-tube, 13.1-metre diameter structure accommodating twin tracks for both up and down lines.

The corporation also highlighted comprehensive safety measures, including settlement markers, piezometers, inclinometers, strain gauges and restricted site access, along with arrangements to pump fresh air for workers inside the tunnel.

The 508 km-long Mumbai-Ahmedabad high-speed rail corridor is India’s first bullet train project.

According to the NHSRCL, work has been completed on 321 km of viaduct, 398 km of pier, along with 17 river bridges, nine steel bridges, and the installation of over four lakh noise barriers across 206 km.

The track bed construction has been finished on 206 km, and more than 2,000 overhead equipment masts have been installed covering 48 km of the mainline viaduct, it stated.

About the Author

News Desk
News Desk

The News Desk is a team of passionate editors and writers who break and analyse the most important events unfolding in India and abroad. From live updates to exclusive reports to in-depth explainers, the Desk d…Read More

The News Desk is a team of passionate editors and writers who break and analyse the most important events unfolding in India and abroad. From live updates to exclusive reports to in-depth explainers, the Desk d… Read More

News india Mumbai-Ahmedabad Bullet Train: First Phase Set To Start In December 2027
Disclaimer: Comments reflect users’ views, not News18’s. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.

Loading comments…

Read More

Go to Source

Hot this week

France’s cybercrime unit searches X’s office in Paris in Grok deepfakes case

In a case related to Grok generating sexually explicit deepfakes, Paris prosecutor’s cybercrime unit has searched the Paris office of X along with French police’s cybercrime unit and Europol. Read More

Did Jeffrey Epstein Father A Secret Child 15 Years Ago? Email In New Files Shows Claim

If accurate, the child referenced in the email would now be approximately 14 or 15 years old. Read More

Why NASA’s Artemis-II Won’t Fly To The Moon In February And What Happens To Astronauts In Quarantine

The four astronauts will now exit quarantine, which began in Houston on January 21st, and re-enter it about two weeks before the next launch attempt in March. Read More

Busy Lives, Silent Risks: Cancer Warning Signs We Miss Every Day

Learn the subtle cancer warning signs often ignored in daily life and why early attention, screenings, and awareness can save lives. Read More

Jodhpuri Kabuli Rice Recipe: The Royal Rajasthani Dish With An Afghan Connection!

Said to have arrived from Afghanistan during the Mughal era, this royal dish blended with Rajasthani spices over time. Read More

Topics

France’s cybercrime unit searches X’s office in Paris in Grok deepfakes case

In a case related to Grok generating sexually explicit deepfakes, Paris prosecutor’s cybercrime unit has searched the Paris office of X along with French police’s cybercrime unit and Europol. Read More

Did Jeffrey Epstein Father A Secret Child 15 Years Ago? Email In New Files Shows Claim

If accurate, the child referenced in the email would now be approximately 14 or 15 years old. Read More

Why NASA’s Artemis-II Won’t Fly To The Moon In February And What Happens To Astronauts In Quarantine

The four astronauts will now exit quarantine, which began in Houston on January 21st, and re-enter it about two weeks before the next launch attempt in March. Read More

Busy Lives, Silent Risks: Cancer Warning Signs We Miss Every Day

Learn the subtle cancer warning signs often ignored in daily life and why early attention, screenings, and awareness can save lives. Read More

Jodhpuri Kabuli Rice Recipe: The Royal Rajasthani Dish With An Afghan Connection!

Said to have arrived from Afghanistan during the Mughal era, this royal dish blended with Rajasthani spices over time. Read More

Breast Cancer And Everyday Choices: How Lifestyle Can Influence Risk And Recovery

Discover how diet, exercise, sleep, and stress management can lower breast cancer risk and support recovery alongside medical treatment. Read More

8 Powerful Health Benefits Of Giloy That Make It India’s Ultimate Immunity Herb

Show Quick Read Key points generated by AI, verified by newsroom Giloy, also known as Guduchi or Amrita in Ayurveda, is more than just a medicinal herb, it is considered the “root of immortality” in ancient Indian texts. Read More

Related Articles